Overall GFA |
|
|
Total Net Leasable Area |
|
|
Number of Levels |
|
|
Building Management |
- Building Management System (BMS)
|
- Building Management System (BMS)
|
Backup Power |
- 100% of the building for 24 hours
|
- 100% of the building for 24 hours
|
Air Conditioning |
- Water-cooled chillers,
Air conditioning capacity inside premises : 199 W/m2
|
- Water-cooled chillers,
Air conditioning capacity inside premises : 185 W/m2
|
Lifts |
- 4 Lifts – Schindler including
Passenger Lift: 3 high-speed lifts with 2.5m/s No. of Stops is 21/21 from Basement 2 to Level 19, Fire/ Service Lift: 1 high-speed lifts with 2.5m/s No. of Stops is 21/21 from Basement 2 to Level 19
|
- 6 Lifts – Schindler including
Passenger Lift: 5 high-speed lifts with 2.5m/s No. of Stops is 18/18 from Basement 2 to Level 16, Fire/ Service Lift: 1 high-speed lifts with 2.5m/s No. of Stops is 18/18 from Basement 2 to Level 16
|
Illumination |
- 545 Lx (International Grade A+ office standard)
|
- 500 Lx (International Grade A+ office standard)
|
Parking |
- 42 parking spaces for cars and 178 parking spaces
for motorbikes in the basements
|
- 96 parking spaces for cars and 665 parking spaces
for motorbikes in the basements
|
For Air Conditioning System
|
- Water-cooled chillers: 2 sets – 2×253 RT (2×890 kW)
|
- Water-cooled chillers: 3×320 RT (3×1,125 kW)
|
For Power Supply
|
- 2 main line medium voltage feeders (22kV) from local
power grid, 1×1,600 kVA dry type transformer in basement 1. 1 stand-by generator with capacity of 1×1,400 kVA (Prime) each as backup for 100% of the building’s requirements.
|
- 2 main line medium voltage feeders (22kV) from local
power grid, 1×2,000 Kva & 1×1,250 kVA dry type transformer in basement 1. 2 stand-by generator with capacity of 2×1,400 kVA (Prime) each as backup for 100% of the building’s requirements.
|